The City has targeted several areas around the community to include sidewalk, ramp and curb repair.

Status

Bidding Closed

Bid Date 8/13/25 10:30am

Company & Contacts

City of Louisburg
Jean Carder  
913-837-2324

Location

Louisburg, KS

Date Issued: 7/23/2025

The City of Louisburg, Kansas, will accept sealed bids for 2025 Concrete Work until the above time, at City Hall, 215 S. Broadway Street, Louisburg, Kansas 66053, 913-837-5371, at which time bids will be opened in a public bid opening.

The proposed work provides for 2025 Concrete Work per Bid Specifications available at Louisburg City Hall during normal business hours. Electronic copies may be obtained by going to www.louisburgkansas.gov or at Drexel Technologies plan room.

A BID AND PERFORMANCE BOND IS REQUIRED.

The City of Louisburg, Kansas, reserves the right to accept or reject any and all proposals, in whole or in part, and to waive technicalities.

Bids may be held by the City of Louisburg, Kansas, for a period not to exceed forty-five (45) days from the date of the opening of the bids for the purposes of reviewing and investigating the bidders’ qualifications, prior to awarding the contract. No bidder may withdraw his bid during this period.

SCOPE OF WORK

The work provided for in these specifications shall consist of furnishing all labor, equipment and miscellaneous materials; and performing all work necessary to complete concrete sidewalk, ramp and curb work to the City’s satisfaction; together with other incidental and related work as set forth in these specifications, or as directed by the Public Works Director, or designated agent, hereafter referred to as the “City”. Services shall be performed in accordance with the specifications provided herein. The bid shall be a unit based amount and shall reflect and include all cost necessary to comply with such provisions.

LOCATION

All work is located in the City of Louisburg, Kansas

SPECIFICATIONS

The City has targeted several areas around the community to include sidewalk, ramp and curb repair. See accompanying map.

Contractor will use AB3 if needed for base.

Curbs shall be stand-up type “B” and have three #4 rebar.

Sidewalks shall have three #4 rebar lengthwise with crossbars. Rebar shall be on chairs.

Sidewalks shall be 4” thick minimum. All sidewalk widths shall match adjoining sidewalks with the exception of the sidewalk at S. Third between Broadway and Mulberry, which will be 5 ft. Sidewalk elevation shall match existing storm sewer inlet.

All concrete shall be KCMMB Granite 4000 psi mix. Concrete mix shall be submitted and approved before pouring. Concrete curb replacement at the 200 W. Amity location should conform to KDOT standards.