EARLY NOTICE - 199th Street from Ridgeview to Renner - Spring Hill, KS
Status
Bidding Closed
| Prebid Date | 9/25/25 12:00pm | 
| Bid Date | 10/9/25 2:00pm | 
Location
Spring Hill, KS
EARLY NOTICE (ONLY)
199TH STREET (RIDGEVIEW TO RENNER)
CONSTRUCTION BID RELEASE
FOR SPRING HILL, KANSAS
SECTION 1: PROJECT OVERVIEW
The City of Spring Hill will be seeking a contractor to improve 199th Street from Ridgeview to Renner. The initial contract will include the improvement of a 2-lane roadway. Additional lanes will be installed as the community grows and develops; this work will be completed separate from the initial proposed 2-lane roadway improvement.
The scope of the roadway improvements will include 2-lane roadway with curb & gutter, enclosed storm sewer, sidewalk, 10-foot concrete trail, and street lighting.
The final plans and specifications will be released in September, with a bid date in October. The chart below includes the tentative schedule.
SECTION 2: TENTATIVE SCHEDULE
The City anticipates the following schedule for the 199th Street Improvements project:
- Wednesday, September 10, 2025 Release Expanded Bid Package 
- Thursday, September 25, 2025 Pre-Bid Meeting 
- Thursday, October 9, 2025 Bids due before 2pm; Bid Opening at 2:05pm 
- October 23, 2025 Finalize Contract / City Council Approval 
- Nov 2025 to Mar 2026 Early Start Allowed 
- March 16, 2026 Official Notice to Proceed 
- November 28, 2026 Substantial Completion Spring 2027 Final Stabilization 
***For more information, please contact Alysen Abel at alysen.abel@springhillks.gov***